PERT analysis is based on
1) Optimistic time
2) Pessimistic time
3) Most Likely Time
1)Optimistic time: This is a best-case scenario. Here the estimate is determined by considering all favorable conditions. This is the shortest duration to complete the task.
2)Pessimistic time: This is a worst-case scenario. Here the estimate is determined by considering all unfavorable conditions; the longest time the activity may take to complete.
3)Most Likely Time: The cost/duration of the activity, based on a realistic effort assessment for the required work and any predicted expenses. The chance of completing an activity is highest within this duration.
307) PERT analysis is based on
Answer is:
all of the above
Explanation:
Related Production and Industrial Engineering MCQ with Answers
Answer is:
all of the above.
Explanation:
Discrepancies of bar chart techniques are
* consequential effects of lack in one activity on omer
* consequential effects of lack in one activity on omer
* free time available for an activity can′t be predicted
Answer is:
consumes neither time nor resources
Answer is: