Discrepancies of bar chart techniques are
* consequential effects of lack in one activity on omer
* consequential effects of lack in one activity on omer
* free time available for an activity can′t be predicted
308) Discrepancies of bar chart techniques are
Answer is:
all of the above.
Explanation:
Related Production and Industrial Engineering MCQ with Answers
Answer is:
consumes neither time nor resources