311) Critical path on PERT/CPM chart is obtained by joining the events having
Answer is:
minimum slack
Related Production and Industrial Engineering MCQ with Answers
Answer is:
a project can be subdivided into a set of predictable, independent activities
Answer is:
anyone of the above
Answer is:
all of the above.
Explanation:
The important file in making a PERT is
* an event can′t be accomplished until activities leading to it are completed
* no activity from any event can be started from preceding event till it is completed
* length of arrow has nothing to do with time