CPM is
* synthesising in concepts
* is built of activities oriented programmes
* is, based on one time estimate
304) CPM is
all of the above.
Related Production and Industrial Engineering MCQ with Answers
all of the above.
A CPM family includes
* CPA (Critical Path Analysis)
* CPP (Critical Path Plotted)
* MCE (Minimum Cost Expenditure)
all of the above.
PERT/CPM, techniques can be used for following
* once through project
* maintenance jobs
* research and development
all of the above
PERT analysis is based on
1) Optimistic time
2) Pessimistic time
3) Most Likely Time
1)Optimistic time: This is a best-case scenario. Here the estimate is determined by considering all favorable conditions. This is the shortest duration to complete the task.
2)Pessimistic time: This is a worst-case scenario. Here the estimate is determined by considering all unfavorable conditions; the longest time the activity may take to complete.
3)Most Likely Time: The cost/duration of the activity, based on a realistic effort assessment for the required work and any predicted expenses. The chance of completing an activity is highest within this duration.
all of the above.
Discrepancies of bar chart techniques are
* consequential effects of lack in one activity on omer
* consequential effects of lack in one activity on omer
* free time available for an activity can′t be predicted