sinking fund method
straight line method
A-B-C charging method
annuity charging method
administrative wing
workshop
foundry shop
stores
latest allowable time and the normal expected time
latest allowable time and the earliest expected time
proposed allowable time and the earliest expected time
normal allowable time and the latest expected time
techniques to determine project status
decision making techniques
charts which increase aesthetic appearance of rooms
aids to the decision maker.
activities and events are clearly shown
early start and late finish of an activity are clearly marked
activity times are clear
inter-relationship among activities is clearly shown.