Answer is:
Man machine chart
Explanation:
A man-machine chart graphically represents the relationship between the manual work performed by one or more operators and one or more machines involved in a manufacturing process.
Answer is:
Production schedule
Explanation:
Gantt charts are commonly used in project and production timeline and resource management where project planning and a multitude of interdependent tasks to be sequenced on one timeline. Horizontal axis bars representing timelines, duration, start-end date, and the completion times of tasks that are involved.
Answer is:
minimise the cost without change ins quality of the product
Explanation:
The aim of value engineering is to Minimize the cost without change in quality of the product.
Answer is:
brainstorming
Explanation:
The value engineering technique in which experts of the same rank assemble for product development is called Brain storming.