P.E.R.T is applied for
* marketing programmes and advertising programmes
* installation of machinery
* research and development of products
54) P.E.R.T is applied for
Answer is:
all of these
Explanation:
Related Industrial Engineering MCQ with Answers
Answer is:
It represents that a programme falls behind schedule and additional resources are required to complete the project in time
Explanation:
When slack of an activity is negative It represents that a programme falls behind schedule and additional resources are required to complete the project in time.
Answer is:
The turning of a job on lathe is an event whereas job turned is an activity.
Explanation:
The performance of a specific task is called an activity.
An event is an instantaneous point in time at which an activity begins or ends.
Answer is:
an arrow
Explanation:
An activity of the project is graphically represented by An arrow on the network diagram.