When slack of an activity is negative It represents that a programme falls behind schedule and additional resources are required to complete the project in time.
55) When slack of an activity is negative
Answer is:
It represents that a programme falls behind schedule and additional resources are required to complete the project in time
Explanation:
Related Industrial Engineering MCQ with Answers
Answer is:
The turning of a job on lathe is an event whereas job turned is an activity.
Explanation:
The performance of a specific task is called an activity.
An event is an instantaneous point in time at which an activity begins or ends.
Answer is:
an arrow
Explanation:
An activity of the project is graphically represented by An arrow on the network diagram.
Answer is:
All of the above
Explanation:
following statement is correct about the network diagram
- The events are represented graphically by circles or nodes at the beginning and the end of activity by arrows.
-The tail end of the arrow represents the start of an activity.
-The head of the arrow represents the end of an activity.