shows the inter dependences of various jobs
depicts the delay of jobs, if any
points outgoing ahead of schedule of jobs, if any
none of the above.
minor works
major works
large projects
all of the above
bar chart method
milestone chart
critical path method (CPM)
programme evaluation and review technique (PERT)
programmer evaluation and review technique is event oriented
programmer evaluation and review technique is not event oriented
critical path method is event oriented
critical path method is an improvement upon bar chart method
critical path method provides a realistic approach to the daily problems
critical path method avoids delays which are very common in bar chart
all of the above.