124) Slack represents the difference between the
Answer is:
latest allowable time and the earliest expected time
Related Production and Industrial Engineering MCQ with Answers
Answer is:
inter-relationship among activities is clearly shown.
Answer is:
activity oriented technique
Explanation:
CPM is activity oriented i.e. CPM network is built on the basis of activities.
CPM is a deterministic model i.e. it does not take into account the uncertainties involved in the estimation of time for execution of a job or an activity.