119) The time required to complete a job is established and a bonus is paid to the worker based on the exact % of time saved. This type of incentive plan is known as
Answer is:
Rowan Plan.
Related Production and Industrial Engineering MCQ with Answers
Answer is:
all of the above
Explanation:
String diagram is one of the useful and simplest techniques of method study.
It can be defined as a scale model on which a thread is used to trace the path or movements of man and materials during a specified sequence of events.
It can also be stated that string diagram in a special form of flow diagram.
Answer is: