PERT or Project Evaluation and Review Technique can be understood as a tool for handling research and development projects which involve a series of activities. It supports the analysis of these actions and their sequential arrangement, along with determining the proposed duration required for completing each of these tasks with the help of drafting a critical path, is termed as PERT analysis.
407) PERT technique of network analysis is mainly useful for
Answer is:
research and development projects
Explanation: